schedule page graphicProject Schedule
 
The project has progressed through an environmental study and final design and is now under construction. While weekly schedule and impact details are available on this site's home page, a general project schedule is listed below.
  • June to November 2006 - Utility relocation project completed
  • September 2006 to Spring 2007- Overpass project begins
    • Detour route is constructed to north of existing 200 N.
    • Initial bridge work begins next to the railroad tracks
    • Retaining wall construction begins near railroad tracks, and fill material is placed
    • Fill material allowed to settle for compaction of the ground underneath
  • Summer 2007 to Summer 2008 - Overpass project continues and is completed
    • Bridgework is completed
    • Roadway construction phases are completed
    • Final aesthetic work on the overpass is completed